Typical timeline by stage
| Stage | Zoho Books launch (per app) | Zoho One / Zoho ERP rollout |
|---|---|---|
| Discover | Days 1–2 | Weeks 1–3 |
| Design | Days 2–3 | Weeks 4–6, with Document |
| Document | User manual, alongside Design | Weeks 4–6 |
| Deploy | Rest of the week | Weeks 7–10 |
| Drive | Hypercare, at least 4 weeks from go-live | Weeks 11–12, then hypercare of up to 3 to 4 months |
How to keep to the timeline
- Appoint one internal project lead with time set aside.
- Start cleaning master data in week one.
- Agree sign-off owners for each stage up front.
- Freeze scope for phase one; park new ideas for phase two.
- Protect time for user testing.